Project: Pound House, Brockmanton, Herefordshire Client : Dr Thompson Brief: Complete Water Harvesting System Installation Completion July 2008 Budget £4.5k
Project: Weatherpost, Clows Top, Worcestershire Client: Private Brief: 420 metres horizontal geothermal ground pipework Completion February 2011 Budget £10k
Project: Harewood End, Hereford District Heating System Client: Duchy of Cornwall Brief: Installation of Biomass Plant Room Completion July 2006 Budget £18k
Project: | Lady Southampton Chapel, Hereford |
Client: | Crump Oakwrights |
Brief: | Vertical Bore Geothermal Heating Installation |
Completion | October 2007 |
Budget | £23k |
Project: Humber Court, Leominster, Herefordshire Client: Mr & Mrs Knight Brief: Aid hot water generation by free solar energy and reduce running costs Completion March 2009 Budget £4.5k
Project: Feathers Hotel, Ledbury, Herefordshire Brief: New restaurant heating. Completion March 2009 Budget £3k
Project: Evesbatch Court Lodge, Worcestershire Architects: Treasure & Son Ltd Brief: Central Heating & Plumbing System Completion December 2008 Budget £13k
Project: Cockshutt, Shropshire Architects: Matthew Allen Associates Brief: Install Central Heating & Water System to 4 Large Properties Completion March 2008 Budget £72k
Project: Grange Farm, Harewood End, Hereford Contractor: Midland Wood Fuels Ltd Brief: Installation of wood chip boiler and district heating system Completion August 2008 Budget £25k
Project: Sudbury House, Faringdon, London Architects: PQR Associates Brief: Complete mechanical service refurbishment Completion May 2002 Budget £1.5m